Planning a first imported chemical delivery

Company news · Eapearl Chemical ·

A first delivery from a new origin tests the route, the paperwork and the site, all at once. Treating it as a project rather than as a purchase is what keeps the material moving.

The critical path runs through documents, not freight

The freight portion of an import is the part most easily bought and the part least likely to fail. What delays a first shipment is almost always a document: a transport declaration prepared for the wrong mode, a certificate that was to be issued after loading and arrived after the goods, an import registration that had to exist before the substance crossed the border rather than after. None of these are difficult individually, and all of them have a lead time.

Write the plan backwards from the date the material is needed on the plant floor. Add the time for incoming checks and release. Add transit, customs clearance and inland movement. Add production and the issue of lot documents at origin. What remains is the date by which the commercial and regulatory questions have to be closed, and it is usually earlier than anyone expects. Assign a named owner on each side to every item on that path, and hold one call to confirm the list before the first booking.

The delivery term is a division of labour

An international trade term does two things: it says where risk passes from seller to buyer, and it allocates who arranges and pays for each step. It does not allocate regulatory duty in the destination, which attaches to the party placing the substance on that market. Confusing the two is the single most common source of a stalled first shipment.

Whatever term is chosen, walk the chain step by step and write a name against each one: export clearance, main carriage, insurance, arrival formalities, duty and tax, port charges, inland leg, unloading at your site. Unloading deserves particular attention, because it is the step most often assumed and least often written down, and because it is the step where your equipment and the carrier equipment have to match. Name the place precisely as well. A term without a named place is an argument waiting to happen.

Paper that travels, and paper that must arrive first

Split the document set in two and treat the halves differently.

  • Ahead of the goods — the safety data sheet in the destination language, any import registration or notification required for that substance, the proforma or commercial invoice needed for clearance, and specification and lot certificate where release depends on them.
  • With the goods — the transport document, the packing list, the certificate of analysis for the actual lot, the certificate of origin where it is required, and the declarations that the transport mode demands for the classification concerned.
  • On the packaging — labelling and marking in the form the destination requires, and transport marks appropriate to the mode. A label that is correct at origin and unacceptable at destination stops a container just as effectively as a missing certificate.

Ask for a sample document pack from a previous shipment before the first order, not after. Reviewing a completed set in advance takes an hour and catches most format problems while they can still be fixed calmly.

Getting the site ready before the booking

The physical side is easier to plan and just as capable of stopping the job. Check that the vehicle can reach the discharge point and turn; check the equipment needed to move the packing that is actually coming, which is a different question for drums, for intermediate containers and for bulk. Confirm that the storage location suits the material: separation from incompatible stock, containment under the store, ventilation, and protection from heat or frost as the material requires.

Compatibility deserves a specific check rather than a general assumption. An acid such as hydrochloric acid and an alkali such as sodium hydroxide must not share containment, and a volatile flammable solvent such as acetone brings ventilation, ignition-source and static requirements that a non-flammable liquid does not. Confirm that the transfer equipment, hoses and seals are compatible with the material and, where relevant, dedicated to it. Brief the people who will be present, including the ones who will not touch the goods but will be working nearby, and make sure spill equipment and the emergency route are in place and known before the day rather than during it.

The day itself, written as a sequence

  1. Check the vehicle and the seal against the transport document before anything is moved.
  2. Verify identity: labels, lot numbers and quantities against the packing list and the order. Stop here if anything disagrees.
  3. Inspect the packing for damage, leakage or signs of exposure, and photograph anything unusual before it is moved.
  4. Sample according to your written procedure, and retain a sealed portion of every lot whether or not you intend to test it now.
  5. Move the goods into a quarantine location that is physically or systematically separated from released stock.
  6. Record the receipt, attach the documents to the lot record, and release only under the rule agreed in advance.

Two people signing the same sequence is better than one, and a short checklist sheet filled in on the day is worth more later than anyone’s recollection of it.

Discrepancies, claims and the record you keep

When something is wrong, the sequence matters more than the speed of the complaint. Stop the material where it stands. Photograph the packing, the labels, the marks and the vehicle. Note the discrepancy on the transport document before the driver leaves, because a clean signature is difficult to argue with afterwards. Keep the retained sample sealed and keep the damaged packing; both are evidence and both tend to be discarded by well-meaning colleagues clearing a working area.

Then notify in writing, within the window your contract provides, stating what was received, what was expected and what evidence exists. A claim succeeds on the quality of the record, not on the strength of the language. Afterwards, hold a short review with the supplier covering what happened and what changes for the next shipment, and write the outcome into the supply agreement rather than into an email that nobody will find. The second delivery should be measurably easier than the first, and that improvement is the real product of doing the first one carefully.

Specifications, sample document packs and shipment planning for a named material and destination can be discussed through our contact page.