Running a joint raw material project with your supplier

Company news · Eapearl Chemical ·

Some raw material changes are a purchase order. Others are a piece of shared technical work in which neither side knows the answer at the start. Confusing the two is expensive, and the confusion usually runs in one direction.

Recognising which one you have

The distinguishing question is whether the specification exists before the work begins. If you can write down what you want to receive, with methods and limits, then you are buying a material and the supplier’s task is to meet it. If the specification is itself one of the things the work has to produce, you are running a project, and treating it as a purchase will fail in a predictable way: the supplier sends samples against a moving target, the buyer reports that none of them are right, and both sides conclude the other is not serious.

Projects of this kind typically arise for one of a few reasons. A regulatory position changes and an established material becomes awkward to keep. A customer imposes a requirement that the current formulation cannot meet. A process is moved to a new site with different equipment. Or a cost structure shifts far enough that a reformulation becomes worth the effort. In each case the requirement is real and the route to it is unknown, which is exactly the condition that shared work is for.

The brief: state the requirement, not the candidate

The most common opening error is to name the wanted material. A brief that asks for a particular ester at a particular purity has already made the technical decision and reduced the supplier to a vendor of that decision. A brief that states what the material must do leaves room for the supplier’s knowledge to be useful, which is the entire reason for involving them.

A workable brief contains the function the material performs in the system, the properties that are genuinely required with the test methods that will be used to judge them, the constraints that cannot move, and an honest account of what the incumbent material does well. That last element is regularly omitted and it matters: without it, the project optimises the property that prompted the change and discovers the sacrificed one at the plant trial.

Who brings what

Contribution Buyer Supplier
Definition Performance requirement, acceptance methods, constraints Candidate chemistries and what is realistically producible
Material The formulation matrix and incumbent reference Samples with lot certificates, plus variants where a grade can be adjusted
Analysis Application testing on the real system Analytical work on the material itself and on impurities in dispute
Knowledge How the material behaves in use and what users complain about Which process parameters can move, and which cannot
Decision A named person who can approve a change A named person who can commit the plant
Continuity Forecast and intent beyond the trial Ability to supply the qualified variant, not just the sample

The two rows most often left empty are the last two, and they are the ones that decide whether the work leads anywhere. A supplier who can produce an excellent sample from a pilot asset but cannot reproduce it at scale has not solved the problem, and it is better to establish that in week one than in month nine.

Gates that both sides sign

Shared work needs decision points that are agreed in advance, with criteria written down and both parties committing to act on the result. The reason to write them is not procedural tidiness. It is that a project without agreed exit criteria never ends; it merely becomes quieter, consuming sample material and attention indefinitely because nobody has authority to declare it finished.

Two properties make a gate real. First, the criteria are stated before the data exist, so that a marginal result cannot be reinterpreted afterwards. Second, failure has a defined consequence, which may be to stop, to redefine the requirement or to try a different chemistry, but is stated rather than improvised. A gate whose only possible outcome is to continue is not a gate.

Confidentiality, ownership and what may be said

Three separate questions get conflated here and each needs its own sentence in the agreement. Confidentiality covers what may be disclosed and for how long, and it has to run in both directions, since the supplier is also revealing process information. Ownership covers who holds the rights to what is created, usually with background knowledge staying where it came from, formulation-specific results going to the buyer and process improvements staying with the supplier. Publicity is separate again: whether either party may name the other, describe the work, or refer to it in any form.

Agree these before samples move. Negotiating ownership after a result exists is a different and far harder conversation, because at that point the value is known and the positions have hardened.

Paying for the work

  1. Bench-scale work is usually absorbed by each side, on the basis that both are investing in a possible outcome.
  2. Plant trials are not symmetric. They consume production capacity and can produce output that cannot be sold, so the cost and its bearer should be stated per trial.
  3. Where a supplier is asked to make a non-standard variant, the minimum economic batch is a real constraint and should be discussed before it becomes a surprise.
  4. Analytical work outside routine scope, particularly method development, is a cost and should be named as one.
  5. If the project succeeds, the price of the qualified material is a fresh commercial negotiation; assuming it will match the incumbent has ended otherwise successful projects.

How it should end

There are three honest endings and only one of them is adoption. The second is shelving: the work produced a viable route that is not worth implementing now, and the finding is written up so that it can be picked up later rather than repeated from scratch. The third is a clear negative: the requirement cannot be met this way, stated plainly and early enough to free both sides for something else.

Write up all three the same way. A project that ends without a document is a project that will be run again by someone who does not know it was run before, which is the most avoidable cost in this entire area. Record what was tried, what the result was, which decision criterion it failed and what would have to change for the conclusion to differ.

Work of this kind is routine across solvent families, from the glycol ether series including propylene glycol monomethyl ether to ester and carbonate alternatives such as propyl acetate and dimethyl carbonate. To scope a technical evaluation against a stated requirement, start through our contact page.